Verrus proposal & emergency moratorium

Moratorium
Verrus — a proposed $5.1 billion data center

After protests at a July council meeting, Salem's city council unanimously passed a data center moratorium at an emergency August session, with a policy framework due by December. The developer advanced its land-use application days before the vote, so whether the moratorium reaches the Verrus project is contested. Verrus says the governor's October statewide permit pause won't affect the project's current stage (Salem Reporter).

Last reviewed October 23, 2026. Something out of date or wrong? Send a correction, anonymously if you like.